Planned improvement at Towcester Road Cemetery

Published: Friday, 28 October 2016

Planned improvement works will be taking place at Towcester Road Cemetery during November.

Work to resurface the footpaths and roadways will begin on Tuesday 1 November and are scheduled to last for approximately four weeks.

In order to minimise disruption, the work will take place in three phases, beginning near the chapel and progressing towards the gate. Northampton Borough Council will also be working with local funeral directors to limit the disruption to any ceremonies due to take place while work is ongoing.